FAS Research Computing - Notishistorik

Alla system fungerar

Status page for the Harvard FAS Research Computing cluster and other resources.

Cluster Utilization (VPN and FASRC login required): Cannon | FASSE


Please scroll down to see details on any Incidents or maintenance notices.
Monthly maintenance occurs on the first Monday of the month (except holidays).

GETTING HELP
Documentation: https://docs.rc.fas.harvard.edu | Account Portal https://portal.rc.fas.harvard.edu
Email: rchelp@rc.fas.harvard.edu | Support Hours


The colors shown in the bars below were chosen to increase visibility for color-blind visitors.
For higher contrast, switch to light mode at the bottom of this page if the background is dark and colors are muted.

I drift

SLURM Scheduler - Cannon - I drift

Cannon Compute Cluster (Holyoke) - I drift

Boston Compute Nodes - I drift

GPU nodes (Holyoke) - I drift

seas_compute - I drift

I drift

SLURM Scheduler - FASSE - I drift

FASSE Compute Cluster (Holyoke) - I drift

I drift

Kempner Cluster CPU - I drift

Kempner Cluster GPU - I drift

I drift

FASSE login nodes - I drift

I drift

Cannon Open OnDemand - I drift

FASSE Open OnDemand - I drift

I drift

Netscratch (Global Scratch) - I drift

Home Directory Storage - Boston - I drift

Tape - (Tier 3) - I drift

Holylabs - I drift

Isilon Storage Holyoke (Tier 1) - I drift

Holystore01 (Tier 0) - I drift

HolyLFS04 (Tier 0) - I drift

HolyLFS05 (Tier 0) - I drift

HolyLFS06 (Tier 0) - I drift

Holyoke Tier 2 NFS (new) - I drift

Holyoke Specialty Storage - I drift

holECS - I drift

Isilon Storage Boston (Tier 1) - I drift

BosLFS02 (Tier 0) - I drift

Boston Tier 2 NFS (new) - I drift

CEPH Storage Boston (Tier 2) - I drift

Boston Specialty Storage - I drift

bosECS - I drift

Samba Cluster - I drift

Globus Data Transfer - I drift

Notishistorik

apr. 2023

Harvard DNS continues to experience outages
  • Löst
    Löst

    As far as we are aware, Harvard's DNS issues are resolved.

  • Identifierat
    Identifierat

    Harvard's DNS (name resolution system which translates hostnames to IP addresses) continues to experience degradation and periodic outages. This issue may affect access to any hostname/address ending in harvard.edu.

    While this should not affect jobs inside the cluster, it will impact other resources users are trying to access including reaching login nodes, VPN, websites, drive mapping, this status page, etc.

    This is a university-wide issue and outside FASRC's control. We will continue to monitor the situation, but for mire information please see Harvard's status page (which may also be inaccessible at times): https://status.huit.harvard.edu/

FASRC Monthly Maintenance April 3rd 2023 7am-11am
  • Slutfört
    april 03, 2023 kl 15:00
    Slutfört
    april 03, 2023 kl 15:00

    Maintenance has completed successfully

  • Pågår
    april 03, 2023 kl 11:00
    Pågår
    april 03, 2023 kl 11:00

    Maintenance is now in progress

  • Planerat
    april 03, 2023 kl 11:00
    Planerat
    april 03, 2023 kl 11:00

    FASRC Monthly Maintenance will occur April 3rd 2023 7am-11am
    Please note that because of the June downtime, we will not hold monthly maintenance in May and July.

    JUNE DOWNTIME AND OS/SOFTWARE CHANGES
    The MGHPCC yearly power downtime will run June 5th-8th with return to full service the morning of Friday June 9th. For timeline and initially details on the downtime, our switch Rocky Linux, and changes to how we do software, please see: https://www.rc.fas.harvard.edu/blog/2023-downtime/

    Also see our Rocky 8 Transition Guide for information on the OS and upcoming test cluster. We will also offer training and consulting in the coming months (TBA). https://docs.rc.fas.harvard.edu/kb/rocky-8-transition-guide/

    Notices about the downtime with links to training, docs, and FAQs will commence in a few weeks.

    TRAINING CALENDAR
    Upcoming new user training and other sessions can be found on our training calendar: https://www.rc.fas.harvard.edu/upcoming-training/

    APRIL 3rd MAINTENANCE

    • Login node and VDI reboots
      -- Audience: Anyone logged into a a login node or VDI/OOD node
      -- Impact: Login and VDI/OOD nodes will rebooted during this maintenance window

    • RCSMB server network changes
      -- Audience: Mounted Samba shares connected at "rcsmb.rc.fas.harvard.edu"
      -- Impact: None expected. The possibility of brief disconnects
      is possible but unlikely.

    • Squid internet proxy update
      -- Audience: Any users/session/process using the internet proxy (https://docs.rc.fas.harvard.edu/kb/proxy-settings/)
      -- Impact: The proxy will be unavailable while updating

    • Scratch cleanup ( https://docs.rc.fas.harvard.edu/kb/policy-scratch/ )
      -- Audience: Cluster users
      -- Impact: Files older than 90 days will be removed.
      planning for a scheduled maintenance during that time.

    Thanks,
    FAS Research Computing
    Department and Service Catalog: https://www.rc.fas.harvard.edu/
    Documentation: https://docs.rc.fas.harvard.edu/
    Status Page: https://status.rc.fas.harvard.edu/

mars 2023

Monthly Maintenance March 6th, 2023 7am-11am
  • Slutfört
    mars 06, 2023 kl 17:06
    Slutfört
    mars 06, 2023 kl 17:06

    Maintenance has completed successfully at 12:00PM.

  • Pågår
    mars 06, 2023 kl 16:30
    Pågår
    mars 06, 2023 kl 16:30

    Maintenance is still in progress as of 11:30AM as one of our vendors needs to complete some hardware work.

    Access to the Slurm scheduler and all compute are still paused, but access to storage and other services has been restored.

    We appreciate your patience.

  • Slutfört
    mars 06, 2023 kl 16:00
    Slutfört
    mars 06, 2023 kl 16:00

    Maintenance has completed successfully

  • Pågår
    mars 06, 2023 kl 12:00
    Pågår
    mars 06, 2023 kl 12:00

    Maintenance is now in progress

  • Planerat
    mars 06, 2023 kl 12:00
    Planerat
    mars 06, 2023 kl 12:00

    NOTICES

    The annual MGHPCC power downtime will take place June 5th-8th, 2023
    Calendar Event: https://www.rc.fas.harvard.edu/events/mghpcc-power-shutdown-2023/
    Blog Post: https://www.rc.fas.harvard.edu/blog/2023-downtime/

    GENERAL MAINTENANCE

    • NOTE: All jobs will be paused during maintenance to reduce heat load and allow data center cooling maintenance to take place.

    • Login node updates and reboots, VDI reboots
      Audience: VDI/OpenOnDemand users
      Impact: VDI will be unavailable during this and the above Slurm upgrade

    • RCSMB (samba) Boston network changes
      Audience: RCSMB shares mounted out of Boston
      Impact: Could cause brief share disconnects during updates

    • UPDATE: Nexus control plane supervisor switchover - ETA 5 minutes, short network disconnect while restarting

    • Login node updates/reboot and VDI node reboots
      Audience: Anyone logged into a a login node or VDI/OOD node
      Impact: Login and VDI/OOD nodes will be unavailable while updating and rebooting

    • Scratch cleanup ( https://docs.rc.fas.harvard.edu/kb/policy-scratch/ )
      Audience: Cluster users
      Impact: Files older than 90 days will be removed.
      Reminder: Scratch 90-day file retention purging runs occur regularly not just during maintenance periods.

    SECURITY UPDATES
    HUIT and the CIO Council have set a goal of reducing risk across all schools within the University. All schools are looking to reduce their outstanding vulnerability count 75% by June 2023. These numbers are based on HUIT security scans of our infrastructure.
    We at FAS Research Computing are responsible for thousands of physical and virtual machines. To make progress in reducing our total open vulnerabilty count, we’re going to update internal and user facing systems as part of scheduled monthly maintenance windows and on a rolling basis outside of these windows. This will generally mean running OS and security updates as needed and rebooting these nodes when required.

    This month, these hosts will get updates as part of our scheduled maintenance:
    boslogin01 - boslogin04
    holylogin01 - holylogin04
    holydtn01 - holydtn04
    xdmod4.rc.fas.harvard.edu
    rchelp.rc.fas.harvard.edu (our ticket system)
    rcsmtp.rc.fas.harvard.edu (our mail system)

    Thanks!
    FAS Research Computing
    Department and Service Catalog: https://www.rc.fas.harvard.edu/
    Documentation: https://docs.rc.fas.harvard.edu/
    Status Page: https://status.rc.fas.harvard.edu/

feb. 2023

Monthly Maintenance Feb. 6th, 2023 7am-11am
  • Slutfört
    februari 06, 2023 kl 16:00
    Slutfört
    februari 06, 2023 kl 16:00

    Maintenance has completed successfully

  • Pågår
    februari 06, 2023 kl 12:00
    Pågår
    februari 06, 2023 kl 12:00

    Maintenance is now in progress

  • Planerat
    februari 06, 2023 kl 12:00
    Planerat
    februari 06, 2023 kl 12:00

    NOTICES

    GPU PARTITIONS
    The gpu_test partition is back in service. Job limits are now 64 cores, 8 GPU's, and 750G of RAM. Users can run up to 2 jobs.

    HOLIDAY NOTICE
    February 20th is a university holiday (Presidents' Day)

    GENERAL MAINTENANCE

    • OnDemand Version upgrade to 2.0.29
      Audience: VDI/OpenOnDemand users
      Impact: VDI will be unavailable during this and the above Slurm upgrade

    • Domain controller updates
      Audience: All cluster
      Impact: Could briefly impact some older systems, otherwise no impact expected

    • Login node and VDI node reboots and firmware updates
      Audience: Anyone logged into a a login node or VDI/OOD node
      Impact: Login and VDI/OOD nodes will be unavailable while updating and rebooting

    • Scratch cleanup ( https://docs.rc.fas.harvard.edu/kb/policy-scratch/ )
      Audience: Cluster users
      Impact: Files older than 90 days will be removed.

    Reminder: Scratch 90-day file retention purging runs occur regularly not just during maintenance periods.

    Thanks!
    FAS Research Computing
    Department and Service Catalog: https://www.rc.fas.harvard.edu/
    Documentation: https://docs.rc.fas.harvard.edu/
    Status Page: https://status.rc.fas.harvard.edu/

feb. 2023 till apr. 2023

Nästa