Annual MGHPCC/Holyoke data center power downtime - May 21-24 2024
影响
维护中 从 1:00 PM 至 9:50 PM
维护中 从 1:00 PM 至 9:50 PM
维护中 从 1:00 PM 至 9:50 PM
维护中 从 1:00 PM 至 9:50 PM
维护中 从 1:00 PM 至 9:50 PM
维护中 从 1:00 PM 至 9:50 PM
- 已完成五月 24, 2024 在 下午 9:50UTC已完成五月 24, 2024 在 下午 9:50UTC
2024 MGHPCC downtime complete
DOWNTIME COMPLETE
The annual multi-day power downtime at MGHPCC (https://www.rc.fas.harvard.edu/blog/2024-mghpcc-power-downtime/) is complete (with any exceptions noted below). Normal service resumes today (Friday May 24th) at 5pm.
The cluster has been updated to Rocky Linux 8.9. Several network, InfiniBand, computer, and storage firmware updates were installed. Available security updates were also installed.
CANNON NODES
More than 90% of nodes are up and all partitions are enabled. If your specialty partition has a downed node, we will attend to this on Tuesday.
FASSE OOD
Some updates are still propagating. If your FASSE Open OnDemand/VDI session does not work initially, please wait or retry your job/session.
POST-DOWNTIME SUPPORT
If you have any further concerns or unanswered questions please submit a help ticket (https://portal.rc.fas.harvard.edu/rcrt/submit_ticket) and we will do our best to respond quickly. Please bear in mind it is a long weekend, so lingering issues may not be dealt with until Tuesday.
Also, have a good long Memorial Day weekend!
Thanks,
FAS Research Computing
https://www.rc.fas.harvard.edu/
https://docs.rc.fas.harvard.edu/
- 更新五月 24, 2024 在 下午 9:08UTC更新五月 24, 2024 在 下午 9:08UTC
We are currently delayed opening the cluster due to some lingering issues.
We will re-open as soon as possible or update again at 6pm.
- 更新五月 24, 2024 在 下午 1:47UTC更新五月 24, 2024 在 下午 1:47UTC
Power work completed by facility. Currently on schedule for powerup and return to service. ETA 5pm.
- 进行中五月 21, 2024 在 下午 1:00UTC进行中五月 21, 2024 在 下午 1:00UTCMaintenance is now in progress
- 已计划五月 21, 2024 在 下午 1:00UTC已计划五月 21, 2024 在 下午 1:00UTC
The 2024 MGHPCC data center annual power downtime will take place May 21-24, 2024.
We will begin our shutdown on Tuesday May 21st and expect a return to service by 5PM Friday May 24th.
- Jobs: Please plan ahead as all still running jobs on the morning of May 21st will be stopped and canceled and will need to be resubmitted after the downtime. Pending jobs will remain in the queue until the cluster returns to regular service on May 24th.
- Access: The cluster, scheduler, login, and OoD nodes will be unavailable for the duration of the downtime. New lab and account requests should wait until after the downtime.
- Storage: All Holyoke storage will be powered down and unavailable for the duration of the downtime. Boston storage will remain online, but your ability to access it may be impacted and network changes may briefly affect its availability.
Further details, an explanation for this year's change in scheduling, a visual timeline, and a list of maintenance tasks overview can be found at:
https://www.rc.fas.harvard.edu/blog/2024-mghpcc-power-downtime/
Progress of the downtime will be posted here on our status page during the event. Note that you can subscribe to receive updates as they happen. Click Get Updates in the upper right.
MAJOR TASK OVERVIEW
OS upgrade to Rocky 8.9 - Point upgrade, no code rebuilds will be required. Switch from system OFED to Mellanox OFED on nodes for improved performance
Infiniband (network) upgrades
BIOS updates (various)
Storage firmware updates
Network Maintenance
Decommission old nodes (targets contacted)
Additional minor one-off updates and maintenance (cable swap, reboots, etc.)
Thanks,
FAS Research Computing