FAS Research Computing - 2026 MGHPCC power downtime June 15-18, 2026 – Vedlikeholdsdetaljer

HolyLFS06 (Tier 0) Opplever redusert ytelse

Status page for the Harvard FAS Research Computing cluster and other resources.

Cluster Utilization (VPN and FASRC login required): Cannon | FASSE


Please scroll down to see details on any Incidents or maintenance notices.
Monthly maintenance occurs on the first Monday of the month (except holidays).

GETTING HELP
Documentation: https://docs.rc.fas.harvard.edu | Account Portal https://portal.rc.fas.harvard.edu
Email: rchelp@rc.fas.harvard.edu | Support Hours


The colors shown in the bars below were chosen to increase visibility for color-blind visitors.
For higher contrast, switch to light mode at the bottom of this page if the background is dark and colors are muted.

2026 MGHPCC power downtime June 15-18, 2026

Fullført
Planlagt juni 15, 2026 kl. 13:00 – juni 18, 2026 kl. 21:15UTC

Påvirker

Cannon Cluster

Vedlikehold fra 1:00 PM til 9:15 PM

SLURM Scheduler - Cannon

Vedlikehold fra 1:00 PM til 9:15 PM

Cannon Compute Cluster (Holyoke)

Vedlikehold fra 1:00 PM til 9:15 PM

Boston Compute Nodes

Vedlikehold fra 1:00 PM til 9:15 PM

GPU nodes (Holyoke)

Vedlikehold fra 1:00 PM til 9:15 PM

seas_compute

Vedlikehold fra 1:00 PM til 9:15 PM

Oppdateringer
  • Fullført
    juni 18, 2026 kl. 21:15UTC
    Fullført
    juni 18, 2026 kl. 21:15UTC

    The yearly power downtime at our Holyoke data center, MGHPCC, has completed.

    The clusters and storage are back online and login nodes and OOD nodes are now available.

    If you have an issue/need help, please send a ticket to rchelp@rc.fas.harvard.edu with details.

    IMPORTANT NOTE: Tomorrow, June 19th is a university holiday. FASRC staff will return Monday to address any lingering issues and any new tickets.

  • Oppdater
    juni 18, 2026 kl. 20:45UTC
    Oppdater
    juni 18, 2026 kl. 20:45UTC

    Power-up is nearly complete, but a delay earlier in the day has us slightly behind.

    New ETA is 6PM.

  • Oppdater
    juni 18, 2026 kl. 12:16UTC
    Oppdater
    juni 18, 2026 kl. 12:16UTC

    MGHPCC has completed their maintenance and restored power to the facility.

    FASRC will now begin the power-up process. Please be aware that this takes several hours.

    We will update this status once complete.

    NOTE: A reminder that tomorrow (Friday) is a university holiday.

  • Pågår
    juni 15, 2026 kl. 13:00UTC
    Pågår
    juni 15, 2026 kl. 13:00UTC
    Maintenance is now in progress
  • Ikke startet ennå
    juni 15, 2026 kl. 13:00UTC
    Ikke startet ennå
    juni 15, 2026 kl. 13:00UTC

    The yearly power downtime at our Holyoke data center, MGHPCC, has been scheduled by the facility. This year's power downtime will take place on Tuesday June  15th - 18th, 2025.  There will be no June monthly maintenance as a result.

    Since the facility will be powered down for two days this year, we will not be performing the usual maintenance tasks. 
    That said, networking and other key infrastructure will be doing maintenance.

    IMPORTANT NOTE: FASRC storage at both Holyoke and Boston will be affected and should not be expected to be available throughout the downtime. Please plan ahead accordingly.

    • Monday June 15th -  Power-down begins at 9AM

    • Tuesday June 16th - Power out at MGHPCC

    • Wednesday June 17th - Power out at MGHPCC

    • Thursday June 18th - Expected return to full service by 5PM

    • Friday June 19th - Please note that June 19th is a university holiday

     

    Monday June 15th -  Power-down begins at 9AM
Tuesday June 16th - Power out at MGHPCC
Wednesday June 17th - Power out at MGHPCC
Thursday June 18th - Expected return to full service by 5PM

    For more detailed information and follow-up, please see:
    https://www.rc.fas.harvard.edu/mghpcc-yearly-shutdown or this Status Page