Monthly maintenance will take place on December 8th. Our maintenance tasks should be completed between 9am-1pm. However:
Additionally, MGHPCC will be performing power upgrades on the odd side of Row 8A where much of our computer resides. This is the final upgrade for this row. Current estimate for this work is a 12 hour window 6am-6pm.
A list of the affected partitions is provided at the bottom of this notice. The nodes in those partitions will be drained prior to the work and will be powered down. Once the work is completed, those nodes will be returned to service.
Notices:
New FASSE partition fasse_gpu_h200. This partitions has 2 H200 nodes and a 3day limit. It is available now.
11/26 - 11/28 are university holidays (Thanksgiving). No on-site support, FASRC staff will return on 12/1.
Training: Upcoming training from FASRC and other sources can be found on our Training Calendar. at https://www.rc.fas.harvard.edu/upcoming-training/
Status Page: You can subscribe to our status to receive notifications of maintenance, incidents, and their resolution at https://status.rc.fas.harvard.edu/ (click Get Updates for options).
We'd love to hear success stories about your or your lab's use of FASRC. Submit your story here.
MAINTENANCE TASKS
Cannon cluster will be paused during this maintenance?: PARTIAL OUTAGE/YES
FASSE cluster will be paused during this maintenance?: PARTIAL OUTAGE/YES
Power work on Row 8A odd
OneFS (Isilon) upgrade
Audience: All Isilon (Tier 1) shares
Impact: Some VMs will be impacted including Cannon OOD, CBScentral, MCZapps/MCZbase, Portal, and Rclic1 (license server)
Slurm upgrade to 25.05.5
Login node reboots
Impacted Cannon Partitions (Full or Partial Outage):