FAS Research Computing - История на известията

Всички системи работят

Status page for the Harvard FAS Research Computing cluster and other resources.

Cluster Utilization (VPN and FASRC login required): Cannon | FASSE


Please scroll down to see details on any Incidents or maintenance notices.
Monthly maintenance occurs on the first Monday of the month (except holidays).

GETTING HELP
Documentation: https://docs.rc.fas.harvard.edu | Account Portal https://portal.rc.fas.harvard.edu
Email: rchelp@rc.fas.harvard.edu | Support Hours


The colors shown in the bars below were chosen to increase visibility for color-blind visitors.
For higher contrast, switch to light mode at the bottom of this page if the background is dark and colors are muted.

Работи

SLURM Scheduler - Cannon - Работи

Cannon Compute Cluster (Holyoke) - Работи

Boston Compute Nodes - Работи

GPU nodes (Holyoke) - Работи

seas_compute - Работи

Работи

SLURM Scheduler - FASSE - Работи

FASSE Compute Cluster (Holyoke) - Работи

Работи

Kempner Cluster CPU - Работи

Kempner Cluster GPU - Работи

Работи

FASSE login nodes - Работи

Работи

Cannon Open OnDemand - Работи

FASSE Open OnDemand - Работи

Работи

Netscratch (Global Scratch) - Работи

Home Directory Storage - Boston - Работи

Tape - (Tier 3) - Работи

Holylabs - Работи

Isilon Storage Holyoke (Tier 1) - Работи

Holystore01 (Tier 0) - Работи

HolyLFS04 (Tier 0) - Работи

HolyLFS05 (Tier 0) - Работи

HolyLFS06 (Tier 0) - Работи

Holyoke Tier 2 NFS (new) - Работи

Holyoke Specialty Storage - Работи

holECS - Работи

Isilon Storage Boston (Tier 1) - Работи

BosLFS02 (Tier 0) - Работи

Boston Tier 2 NFS (new) - Работи

CEPH Storage Boston (Tier 2) - Работи

Boston Specialty Storage - Работи

bosECS - Работи

Samba Cluster - Работи

Globus Data Transfer - Работи

История на известията

апр 2023

Harvard DNS continues to experience outages
  • Решен
    Решен

    As far as we are aware, Harvard's DNS issues are resolved.

  • Идентифициран
    Идентифициран

    Harvard's DNS (name resolution system which translates hostnames to IP addresses) continues to experience degradation and periodic outages. This issue may affect access to any hostname/address ending in harvard.edu.

    While this should not affect jobs inside the cluster, it will impact other resources users are trying to access including reaching login nodes, VPN, websites, drive mapping, this status page, etc.

    This is a university-wide issue and outside FASRC's control. We will continue to monitor the situation, but for mire information please see Harvard's status page (which may also be inaccessible at times): https://status.huit.harvard.edu/

FASRC Monthly Maintenance April 3rd 2023 7am-11am
  • Завършен
    април 03, 2023 в 15:00
    Завършен
    април 03, 2023 в 15:00

    Maintenance has completed successfully

  • В ход
    април 03, 2023 в 11:00
    В ход
    април 03, 2023 в 11:00

    Maintenance is now in progress

  • Планиран
    април 03, 2023 в 11:00
    Планиран
    април 03, 2023 в 11:00

    FASRC Monthly Maintenance will occur April 3rd 2023 7am-11am
    Please note that because of the June downtime, we will not hold monthly maintenance in May and July.

    JUNE DOWNTIME AND OS/SOFTWARE CHANGES
    The MGHPCC yearly power downtime will run June 5th-8th with return to full service the morning of Friday June 9th. For timeline and initially details on the downtime, our switch Rocky Linux, and changes to how we do software, please see: https://www.rc.fas.harvard.edu/blog/2023-downtime/

    Also see our Rocky 8 Transition Guide for information on the OS and upcoming test cluster. We will also offer training and consulting in the coming months (TBA). https://docs.rc.fas.harvard.edu/kb/rocky-8-transition-guide/

    Notices about the downtime with links to training, docs, and FAQs will commence in a few weeks.

    TRAINING CALENDAR
    Upcoming new user training and other sessions can be found on our training calendar: https://www.rc.fas.harvard.edu/upcoming-training/

    APRIL 3rd MAINTENANCE

    • Login node and VDI reboots
      -- Audience: Anyone logged into a a login node or VDI/OOD node
      -- Impact: Login and VDI/OOD nodes will rebooted during this maintenance window

    • RCSMB server network changes
      -- Audience: Mounted Samba shares connected at "rcsmb.rc.fas.harvard.edu"
      -- Impact: None expected. The possibility of brief disconnects
      is possible but unlikely.

    • Squid internet proxy update
      -- Audience: Any users/session/process using the internet proxy (https://docs.rc.fas.harvard.edu/kb/proxy-settings/)
      -- Impact: The proxy will be unavailable while updating

    • Scratch cleanup ( https://docs.rc.fas.harvard.edu/kb/policy-scratch/ )
      -- Audience: Cluster users
      -- Impact: Files older than 90 days will be removed.
      planning for a scheduled maintenance during that time.

    Thanks,
    FAS Research Computing
    Department and Service Catalog: https://www.rc.fas.harvard.edu/
    Documentation: https://docs.rc.fas.harvard.edu/
    Status Page: https://status.rc.fas.harvard.edu/

мар 2023

Monthly Maintenance March 6th, 2023 7am-11am
  • Завършен
    март 06, 2023 в 17:06
    Завършен
    март 06, 2023 в 17:06

    Maintenance has completed successfully at 12:00PM.

  • В ход
    март 06, 2023 в 16:30
    В ход
    март 06, 2023 в 16:30

    Maintenance is still in progress as of 11:30AM as one of our vendors needs to complete some hardware work.

    Access to the Slurm scheduler and all compute are still paused, but access to storage and other services has been restored.

    We appreciate your patience.

  • Завършен
    март 06, 2023 в 16:00
    Завършен
    март 06, 2023 в 16:00

    Maintenance has completed successfully

  • В ход
    март 06, 2023 в 12:00
    В ход
    март 06, 2023 в 12:00

    Maintenance is now in progress

  • Планиран
    март 06, 2023 в 12:00
    Планиран
    март 06, 2023 в 12:00

    NOTICES

    The annual MGHPCC power downtime will take place June 5th-8th, 2023
    Calendar Event: https://www.rc.fas.harvard.edu/events/mghpcc-power-shutdown-2023/
    Blog Post: https://www.rc.fas.harvard.edu/blog/2023-downtime/

    GENERAL MAINTENANCE

    • NOTE: All jobs will be paused during maintenance to reduce heat load and allow data center cooling maintenance to take place.

    • Login node updates and reboots, VDI reboots
      Audience: VDI/OpenOnDemand users
      Impact: VDI will be unavailable during this and the above Slurm upgrade

    • RCSMB (samba) Boston network changes
      Audience: RCSMB shares mounted out of Boston
      Impact: Could cause brief share disconnects during updates

    • UPDATE: Nexus control plane supervisor switchover - ETA 5 minutes, short network disconnect while restarting

    • Login node updates/reboot and VDI node reboots
      Audience: Anyone logged into a a login node or VDI/OOD node
      Impact: Login and VDI/OOD nodes will be unavailable while updating and rebooting

    • Scratch cleanup ( https://docs.rc.fas.harvard.edu/kb/policy-scratch/ )
      Audience: Cluster users
      Impact: Files older than 90 days will be removed.
      Reminder: Scratch 90-day file retention purging runs occur regularly not just during maintenance periods.

    SECURITY UPDATES
    HUIT and the CIO Council have set a goal of reducing risk across all schools within the University. All schools are looking to reduce their outstanding vulnerability count 75% by June 2023. These numbers are based on HUIT security scans of our infrastructure.
    We at FAS Research Computing are responsible for thousands of physical and virtual machines. To make progress in reducing our total open vulnerabilty count, we’re going to update internal and user facing systems as part of scheduled monthly maintenance windows and on a rolling basis outside of these windows. This will generally mean running OS and security updates as needed and rebooting these nodes when required.

    This month, these hosts will get updates as part of our scheduled maintenance:
    boslogin01 - boslogin04
    holylogin01 - holylogin04
    holydtn01 - holydtn04
    xdmod4.rc.fas.harvard.edu
    rchelp.rc.fas.harvard.edu (our ticket system)
    rcsmtp.rc.fas.harvard.edu (our mail system)

    Thanks!
    FAS Research Computing
    Department and Service Catalog: https://www.rc.fas.harvard.edu/
    Documentation: https://docs.rc.fas.harvard.edu/
    Status Page: https://status.rc.fas.harvard.edu/

фев 2023

Monthly Maintenance Feb. 6th, 2023 7am-11am
  • Завършен
    февруари 06, 2023 в 16:00
    Завършен
    февруари 06, 2023 в 16:00

    Maintenance has completed successfully

  • В ход
    февруари 06, 2023 в 12:00
    В ход
    февруари 06, 2023 в 12:00

    Maintenance is now in progress

  • Планиран
    февруари 06, 2023 в 12:00
    Планиран
    февруари 06, 2023 в 12:00

    NOTICES

    GPU PARTITIONS
    The gpu_test partition is back in service. Job limits are now 64 cores, 8 GPU's, and 750G of RAM. Users can run up to 2 jobs.

    HOLIDAY NOTICE
    February 20th is a university holiday (Presidents' Day)

    GENERAL MAINTENANCE

    • OnDemand Version upgrade to 2.0.29
      Audience: VDI/OpenOnDemand users
      Impact: VDI will be unavailable during this and the above Slurm upgrade

    • Domain controller updates
      Audience: All cluster
      Impact: Could briefly impact some older systems, otherwise no impact expected

    • Login node and VDI node reboots and firmware updates
      Audience: Anyone logged into a a login node or VDI/OOD node
      Impact: Login and VDI/OOD nodes will be unavailable while updating and rebooting

    • Scratch cleanup ( https://docs.rc.fas.harvard.edu/kb/policy-scratch/ )
      Audience: Cluster users
      Impact: Files older than 90 days will be removed.

    Reminder: Scratch 90-day file retention purging runs occur regularly not just during maintenance periods.

    Thanks!
    FAS Research Computing
    Department and Service Catalog: https://www.rc.fas.harvard.edu/
    Documentation: https://docs.rc.fas.harvard.edu/
    Status Page: https://status.rc.fas.harvard.edu/

фев 2023 до апр 2023

Следващ