FAS Research Computing - MGHPCC power work - Part 1 May 11 – Maintenance details
All systems operational
Status page for the Harvard FAS Research Computing cluster and other resources.
Cluster Utilization (VPN and FASRC login required): Cannon | FASSE
Please scroll down to see details on any Incidents or maintenance notices.
Monthly maintenance occurs on the first Monday of the month (except holidays).
The colors shown in the bars below were chosen to increase visibility for color-blind visitors. For higher contrast, switch to light mode at the bottom of this page if the background is dark and colors are muted.
MGHPCC power work - Part 1 May 11
Completed
Scheduled for May 11, 2026 at 11:00 AM – May 16, 2026 at 11:00 PM
Affects
Cannon Cluster
Under maintenance from 11:00 AM to 11:00 PM
SLURM Scheduler - Cannon
Under maintenance from 11:00 AM to 11:00 PM
Cannon Compute Cluster (Holyoke)
Under maintenance from 11:00 AM to 11:00 PM
Boston Compute Nodes
Under maintenance from 11:00 AM to 11:00 PM
GPU nodes (Holyoke)
Under maintenance from 11:00 AM to 11:00 PM
seas_compute
Under maintenance from 11:00 AM to 11:00 PM
Updates
Completed
May 16, 2026 at 11:00 PM
Completed
May 16, 2026 at 11:00 PM
Maintenance has completed successfully
In progress
May 11, 2026 at 11:00 AM
In progress
May 11, 2026 at 11:00 AM
Maintenance is now in progress
Update
May 11, 2026 at 11:00 AM
Update
May 11, 2026 at 11:00 AM
Rescheduled to May 11
Planned
May 11, 2026 at 11:00 AM
Planned
May 11, 2026 at 11:00 AM
Our Holyoke data center, MGHPCC, will be doing power work on Row 8A. This work, which will occur this week and next week, will bring online another power feed which will increase power capacity.
In order to do this work, it will require us to idle half the nodes in 8a for the duration of the week. This means all partitions in this row will be at half capacity. Existing jobs should drain naturally and no job should need to be canceled.