FAS Research Computing - Nodes down – Hendelsesdetaljer

Opplever delvis svekket ytelse

Status page for the Harvard FAS Research Computing cluster and other resources.

Cluster Utilization (VPN and FASRC login required): Cannon | FASSE


Please scroll down to see details on any Incidents or maintenance notices.
Monthly maintenance occurs on the first Monday of the month (except holidays).

GETTING HELP
Documentation: https://docs.rc.fas.harvard.edu | Account Portal https://portal.rc.fas.harvard.edu
Email: rchelp@rc.fas.harvard.edu | Support Hours


The colors shown in the bars below were chosen to increase visibility for color-blind visitors.
For higher contrast, switch to light mode at the bottom of this page if the background is dark and colors are muted.

Nodes down

Løst
Delvis brudd
Begynte på over ett år sidenVarte 34 minutter

Påvirket

Cannon Cluster

Delvis brudd fra 2:08 PM til 2:42 PM

Cannon Compute Cluster (Holyoke)

Delvis brudd fra 2:08 PM til 2:42 PM

External Resources - Data Centers

Delvis brudd fra 2:08 PM til 2:42 PM

Holyoke/MGHPCC Data Center

Delvis brudd fra 2:08 PM til 2:42 PM

Oppdateringer
  • Løst
    Løst
    Affected nodes have been restored. Jobs on the nodes that went down will automatically requeue.
  • Identifisert
    Identifisert
    Due to a power glitch at MGHPCC some nodes are down. We are working to restore. You may have noticed some jobs re-queued overnight.