FAS Research Computing - Cannon cluster degraded – Hændelsesdetaljer

Oplever delvist forringet ydeevne

Status page for the Harvard FAS Research Computing cluster and other resources.

Cluster Utilization (VPN and FASRC login required): Cannon | FASSE


Please scroll down to see details on any Incidents or maintenance notices.
Monthly maintenance occurs on the first Monday of the month (except holidays).

GETTING HELP
Documentation: https://docs.rc.fas.harvard.edu | Account Portal https://portal.rc.fas.harvard.edu
Email: rchelp@rc.fas.harvard.edu | Support Hours


The colors shown in the bars below were chosen to increase visibility for color-blind visitors.
For higher contrast, switch to light mode at the bottom of this page if the background is dark and colors are muted.

Cannon cluster degraded

Løst
Begrænset drift
Påbegyndt næsten 2 år sidenVarede cirka 5 timer

Påvirket

Cannon Cluster

Begrænset drift fra 2:22 PM til 7:19 PM

SLURM Scheduler - Cannon

Begrænset drift fra 2:22 PM til 7:19 PM

Cannon Compute Cluster (Holyoke)

Begrænset drift fra 2:22 PM til 7:19 PM

Boston Compute Nodes

Begrænset drift fra 2:22 PM til 7:19 PM

GPU nodes (Holyoke)

Begrænset drift fra 2:22 PM til 7:19 PM

seas_compute

Begrænset drift fra 2:22 PM til 7:19 PM

Opdateringer
  • Løst
    Løst
    The power issue has been resolved. All nodes that were drained are now being re-opened.
  • Undersøger
    Undersøger

    Due to temporary power availability issues in MGHPCC, half the nodes in 8A have been set to drain. This affects all partitions. Jobs will take longer to schedule but will not be terminated.

    We will reopen these nodes once the power issue has been resolved at the datacenter. No ETA at this time