FAS Research Computing - MGHPCC power work 5/21 - 5/23 - Some partitions will be at half capacity – Maintenance details
All systems operational
Status page for the Harvard FAS Research Computing cluster and other resources.
Cluster Utilization (VPN and FASRC login required): Cannon | FASSE
Please scroll down to see details on any Incidents or maintenance notices.
Monthly maintenance occurs on the first Monday of the month (except holidays).
The colors shown in the bars below were chosen to increase visibility for color-blind visitors. For higher contrast, switch to light mode at the bottom of this page if the background is dark and colors are muted.
MGHPCC power work 5/21 - 5/23 - Some partitions will be at half capacity
Planned
Scheduled for May 21, 2025 at 11:00 AM – May 23, 2025 at 7:00 PM
The MGHPCC Holyoke data center will be performing power work on May 21st -23rd. This work will take out one half (or one 'side') of the power capacity for certain rows/racks including our compute rows. Because of our power draw, one side is not enough power to keep each full rack running.
As such, we will be adding a reservation to idle half the nodes in the partitions listed below. A reservation will cause nodes to drain as jobs complete and stop scheduling new jobs on those nodes if they cannot be completed before the outage. This will allow us to idle and power down those nodes prior to the work and avoid potential blackout/brownout on those racks.
This will mean that these partitions will be up and available, but that half the nodes from each will be down (assuming an even number of nodes).
This work is part of an on-going power capacity upgrade at MGHPCC. We expect this will be the last power work needed and the facility will then provide enough additional power for future expansion as well adding overhead for the current load.